Stockton Parkway, Alexandria

Project Timeline: 110 Days

Scope: This project was an in-house Moore Construction Group build. We acquired this waterfront property based on a referral from a local Realtor, and will be placing it back on the market in the beginning of March, 2019. This project included a full gut down to the exterior walls of the existing structure, total reconfiguration, a master suite addition above the garage, and large rear addition with 2nd story terrace.

51826023_10156572018218122_3084568889770639360_o_10156572018213122.jpg

After

Before

Along the way

Work Done:

  • In-house Architectural Design and permitting

  • Gut demolition of interior, fixtures, finishes, framing, and rear solarium

  • Framing of entirely new layout

  • Construction of rear addition and terrace

  • Construction of front addition for master suite

  • All new plumbing, electrical, and HVAC systems

  • 4 new full bathrooms and one powder room

  • Large open concept kitchen

  • Large full service wet bar

  • New roofing and siding throughout

  • New driveway

  • Site excavation and landscaping

  • Permitting, design and construction of 185’ dock

    • Sub panel for yacht 50AMP power

    • High pressure water to front and end of the dock

    • Waterproof LED lighting from end to end

Independence Ave SE

Project Timeline: 4 Months

Scope: This project was a complete gut with a new stairway location.  We installed all new plumbing, electrical and HVAC systems, and completely re-designed the space including adding an additional full bath.

After

Before

Work Done:

  • Coordination of all permitting requirements
  • Complete re-design and build out of entire house
  • All new HVAC, plumbing and electrical
  • New Kitchen and bathroom
  • Add a full bathroom

10th St NE

Project Timeline: 6 Months

Scope: This project was a complete gut with new top-story addition and rear deck.  We installed all new plumbing, electrical and HVAC systems, completely re-designed the space, and added a full bathroom.

After

Before

Work Done:

  • Coordination of all permitting requirements
  • Complete re-design and build out of entire house including additions
  • All new HVAC, plumbing and electrical to include upgrading the electrical service panel
  • New rear deck
  • New Kitchen and bathrooms
  • Exterior work and siding

Alabama Ave, SE DC

Project Timeline: 75 Days

Scope: This project was brought to us by our customer with consideration of tearing down the structure all together.  Once onsite discussing budget and timeline, after searching out the help of our Structural Engineer and on staff Architectural Design team; Moore Construction Group was tasked with this extensive renovation which included the following highlights.

After

Before

Work Done:

  • Coordination of all permitting requirements
  • Demolition of failing 2 car garage
  • Leveling of basement and main level flooring system
  • Framing throughout to accommodate new design and layout, reframing to maximize the height of the ceilings in the bedrooms by vaulting the ceilings to include a small addition to enclose the front of the original porch
  • All new HVAC, plumbing and electrical to include upgrading the electrical service panel
  • New porch, columns, siding and deck
  • New structural retaining walls with steps and lead walk
  • New 2 car parking pad